<< Click to display table of contents >> Navigation: TiCon Takt > Mix balancing > Mode of operation |
The following steps have to be performed to create a mix balancing:
Create new balancing element |
|
Name balancing, |
|
Workplace organization and variants must be defined |
|
Create resources (assembly line / stations / operators / machines) |
|
Assign processes |
|
|
Header |
|
Workplace organization Variants |
|
Assignment |
|
Assignment |
Work steps
1.Open new mix balancing via the context menu or the "+" button in the "Start" ribbon
2. "Abtaktung benennen" and optionally assign data basis and/or assembly line
2.Define "Arbeitsplatzorganisation" and "Varianten"
3."Ressourcen anlegen" (assembly line / stations / operators / machines)
Note |
The mode of operation depicted is only a suggestion. There are a number of possible procedures that differ from use case to use case. |
Note |
The type of balancing cannot be changed later |