Workplace Organization

<< Click to display table of contents >>

Navigation:  TiCon Takt > General tabs >

Workplace Organization

In the "Workplace organization" tab, the general conditions of the workplace and the criteria for evaluating physical strains are displayed and edited.

The input mode must be selected before any entries are made. This determines the further procedure and the resulting entries.

Tab Workplace organization

Tab Workplace organization

The following possible entries are available:

Input mode

Calculation of

Mode inactive because no variant exists.

Number of cycles/Working time (net)

Cycle time


Number of cycles/Working time (gross)

Cycle time


Number of cycles/cycle time

Working time (net), Working time (gross)


Number of cycles

Working time (net), cycle time (flexible*)


Working time (net) / cycle time

Number of cycles

x

Working time (gross) / cycle time

Number of cycles

x

Working time (net)

Number of Cycles, Cycle Time (Flexible*)

x

Working time (gross)

Number of Cycles, Cycle Time (Flexible*)

x

Some input fields are inactive until at least one product variant exists.

* The highest volume of work or the most efficient worker gives the cycle time.

Definition:

Number of cycles = Total quantity

Shift duration (net) = Working time (net)

Shift duration (gross) = Working time (gross)

Please note:

In the Administration, it is possible to define the input mode and all other values and specify them, if necessary, at the element configuration of the balancing in the tab Workplace organization.

Breaks

It is possible to maintain a list for breaks in the administration. In the Workplace Organization tab of a balancing, pauses can be added or deleted using the Add button and the Delete button in the ribbon.

This is also possible using the Plus icon or the Minus icon directly in the corresponding row.

Pauses can be added or deleted if changes are permitted.

takt_workplace_organisation_break

Unit

By clicking on the unit in the row to be edited, a menu opens where you can enter the value in the desired time unit. This saves effort when converting.

takt_time_unit

Workplace organization in mix balancing and maximum balancing

In a mix balancing or maximum balancing, the number of cycles is not freely selectable, but is calculated from the number of pieces of the variants.

Workplace organization in mix balancing and maximum balancing

Workplace organization in mix balancing and maximum balancing