<< Click to display table of contents >> Navigation: TiCon Base > MTM, MTM-1 and MTM-2 Analysis > MTM Analysis > MTM Analysis - Examples > MTM-Analysis with process indicator "Value Added" > Set/Overwrite value adding in structure |
The structure of the analysis B.M.AB3.03.5 was evaluated in relation to the value added. B.M.AB3.03.5 is used in C.M.AB3K...5. The corresponding structure row in C.M.AB3K...5 is set to "non-value adding" in relation to the value added. As a result, the shares of the value added are changed from B.M.AB3.03.5 to C.M.AB3K...5.
Using B.M.AB3.03.5 in C.M.AB3K...5 without assigning a value adding:

Analysis B.M.AB3.03.5:

Analysis B.M.AB3.03.5: Structure with value adding and the "Value added" tab
Assignment of the value adding "non-value adding" in structure line of C.M.AB3K...5:

Allocation of the value adding for the structure element B.M.AB3.03.5 in the structure of the analysis C.M.AB3K...5
Evaluation in the tab "Value added" in C.M.AB3K...5:

Shares of value added from analysis B.M.AB3.03.5 are overwritten in analysis C.M.AB3K...5