Set/Overwrite value adding in structure

<< Click to display table of contents >>

Navigation:  TiCon Base > MTM, MTM-1 and MTM-2 Analysis > MTM Analysis > MTM Analysis - Examples > MTM-Analysis with process indicator "Value Added" >

Set/Overwrite value adding in structure

The structure of the analysis B.M.AB3.03.5 was evaluated in relation to the value added. B.M.AB3.03.5 is used in C.M.AB3K...5. The corresponding structure row in C.M.AB3K...5 is set to "non-value adding" in relation to the value added. As a result, the shares of the value added are changed from B.M.AB3.03.5 to C.M.AB3K...5.

Using B.M.AB3.03.5 in C.M.AB3K...5 without assigning a value adding:

PBS_WS_BSP_2

Analysis B.M.AB3.03.5:

PBS_WS_BSP_1

Analysis B.M.AB3.03.5: Structure with value adding and the "Value added" tab

Assignment of the value adding "non-value adding" in structure line of C.M.AB3K...5:

PBS_WS_BSP_4

Allocation of the value adding for the structure element B.M.AB3.03.5 in the structure of the analysis C.M.AB3K...5

Evaluation in the tab "Value added" in C.M.AB3K...5:

PBS_WS_BSP_5

Shares of value added from analysis B.M.AB3.03.5 are overwritten in analysis C.M.AB3K...5